Trump administration defends Keystone XL pipeline in court

Featured Articles

Trump administration attorneys defended the disputed Keystone XL oil sands pipeline in federal court on Thursday against environmentalists and Native American groups that want to derail the project.

President Barack Obama rejected the 1,179-mile (1,800-kilometer) line proposed by TransCanada Corporation in 2015 because of its potential to exacerbate climate change.

President Donald Trump revived the project soon after taking office last year, citing its potential to create jobs and advance energy independence.

Environmentalists and Native American groups sued to stop the line and asked U.S. District Judge Brian Morris to halt the project. They and others, including landowners, are worried about spills that could foul groundwater and the pipeline's impacts to their property rights.

Morris did not immediately rule following a four-hour Thursday hearing in federal court in Great Falls.

U.S. government attorneys asserted that Trump's change in course from Obama's focus on climate change reflected a legitimate shift in policy, not an arbitrary rejection of previous studies of the project.

"While the importance of climate change was considered, the interests of energy security and economic development outweighed those concerns," the attorneys recently wrote.

Morris previously rejected a bid by the administration to dismiss the lawsuit on the grounds that Trump had constitutional authority over the pipeline as a matter of national security.

Keystone XL would cost an estimated $8 billion. It would begin in Alberta and transport up to 830,000 barrels a day of crude through Montana and South Dakota to Nebraska, where it would connect with lines to carry oil to Gulf Coast refineries.

Federal approval is required because the route crosses an international border.

TransCanada, based in Calgary, said in court submissions that the pipeline would operate safely and help reduce U.S. reliance on crude from the Middle East and other regions.

The project is facing a separate legal challenge in Nebraska, where landowners have filed a lawsuit challenging the Nebraska Public Service Commission's decision to approve a route through the state.

Related listings

  • Kentucky high court: Death penalty IQ law unconstitutional

    Kentucky high court: Death penalty IQ law unconstitutional

    Featured Articles 06/16/2018

    The Kentucky Supreme Court has ruled that the state's practice for determining if someone is intellectually disabled and not eligible to receive the death penalty is "unconstitutional."News outlets report that the court on Thursday deemed Kentucky's ...

  • Kansas court avoids ruling on execution for student's death

    Kansas court avoids ruling on execution for student's death

    Featured Articles 06/14/2018

    The Kansas Supreme Court has postponed a decision on whether the state can execute a man convicted of kidnapping, raping and strangling a 19-year-old college student.The high court on Friday upheld the capital murder conviction of Justin Eugene Thurb...

  • Ohio's top court to hear arguments on promotions tax dispute

    Ohio's top court to hear arguments on promotions tax dispute

    Featured Articles 06/11/2018

    The Ohio Supreme Court plans to hear arguments in a dispute over promotions including bobbleheads and other items offered by the Cincinnati Reds to ticket buyers.At issue is whether the Reds are exempt from paying tax on the purchase of the promotion...

USCIS Issues Clarifying Guidance on NAFTA TN Status Eligibility for Economists

U.S. Citizenship and Immigration Services (USCIS) announced today that it is clarifying policy guidance (PDF, 71 KB) on the specific work activities its officers should consider when determining whether an individual qualifies for TN nonimmigrant status as an economist.

The North American Free Trade Agreement (NAFTA) TN nonimmigrant status allows qualified Canadian and Mexican citizens to temporarily enter the U.S. to engage in specific professional activities, including the occupation of economist. The agreement, however, does not define the term economist, resulting in inconsistent decisions on whether certain analysts and financial professionals qualify for TN status as economists.

TN nonimmigrant status is intended to allow a limited number of professionals and specialists to work temporarily in certain specifically identified occupations in the United States. This updated guidance provides USCIS officers with a specific definition of one such category – economists – allowing them to adjudicate applications in a way that complies with the intent of the agreement. This policy update clarifies that professional economists requesting TN status must engage primarily in activities consistent with the profession of an economist. Individuals who work primarily in other occupations related to the field of economics — such as financial analysts, marketing analysts, and market research analysts — are not eligible for classification as a TN economist.