Court raises concerns over power lines by historic Jamestown
National News
A federal appeals court raised concerns Friday that power lines with towers nearly as high as the Statue of Liberty could spoil the view in one of the nation's most historically rich areas, a stretch of river in Virginia where England founded its first permanent settlement.
The power lines cross the James River near Jamestown Island. And they began transmitting 500,000 volts of electricity on Tuesday.
Despite the project's completion, the court directed the U.S. Army Corps of Engineers to prepare a full environmental impact statement for the project. The agency previously deemed it to be unnecessary.
The appeals court found that the Corps failed to fully consider the project's impact before issuing a permit to Dominion Energy. The ruling also said the Corps failed to resolve concerns that were raised in many of the 50,000 public comments that were submitted and by other federal agencies over the years.
For instance, the National Park Service has said utility lines should be run underground in the area, allowing people to experience views similar to what English explorer John Smith saw in the early 1600s.
Related listings
-
Supreme Court seems inclined to retain cross on public land
National News 03/01/2019The Supreme Court seemed inclined Wednesday to rule that a 40-foot-tall cross that stands on public land in Maryland is constitutional, but shy away from a sweeping ruling.The case the justices heard arguments in is being closely watched because it i...
-
Alec Baldwin appears in court in parking-spot case
National News 12/02/2018Alec Baldwin appeared in a New York court on Monday after being accused of striking a man in the face over a parking space.The 60-year-old actor said nothing as he was arraigned on misdemeanor and violation-level charges. He has previously stated tha...
-
Rancorous, partisan start for Kavanaugh high court hearing
National News 09/02/2018Supreme Court nominee Brett Kavanaugh declared fervently at his Senate confirmation hearing Tuesday the court "must never, never be viewed as a partisan institution." But that was at the end of a marathon day marked by rancorous exchanges between Dem...
USCIS Will Begin Accepting CW-1 Petitions for Fiscal Year 2019
On April 2, 2018, U.S. Citizenship and Immigration Services (USCIS) will begin accepting petitions under the Commonwealth of the Northern Mariana Islands (CNMI)-Only Transitional Worker (CW-1) program subject to the fiscal year (FY) 2019 cap. Employers in the CNMI use the CW-1 program to employ foreign workers who are ineligible for other nonimmigrant worker categories. The cap for CW-1 visas for FY 2019 is 4,999.
For the FY 2019 cap, USCIS encourages employers to file a petition for a CW-1 nonimmigrant worker up to six months in advance of the proposed start date of employment and as early as possible within that timeframe. USCIS will reject a petition if it is filed more than six months in advance. An extension petition may request a start date of Oct. 1, 2018, even if that worker’s current status will not expire by that date.
Since USCIS expects to receive more petitions than the number of CW-1 visas available for FY 2019, USCIS may conduct a lottery to randomly select petitions and associated beneficiaries so that the cap is not exceeded. The lottery would give employers the fairest opportunity to request workers, particularly with the possibility of mail delays from the CNMI.
USCIS will count the total number of beneficiaries in the petitions received after 10 business days to determine if a lottery is needed. If the cap is met after those initial 10 days, a lottery may still need to be conducted with only the petitions received on the last day before the cap was met. USCIS will announce when the cap is met and whether a lottery has been conducted.